Question: 

Are wood trusses designed to be fall protection anchors that would support a worker should he fall?

Question: 

My company supplied roof trusses for a hotel project. The building inspector shut the project down because the trusses were not designed to account for additional snowdrift loading. The construction plans did not contain any snowdrift loading information. The architect is claiming it is our responsibility to determine drift loading, therefore we must fix the problem. Do you have any documentation to help us dispute the architect’s claim?

Question: 

Would you please inform me of the specified requirements of the size and the amount of nail attachments from the truss to the top plate?

Question: 

Is there a chart available on the allowable amount of deflection on floor trusses?

Question: 

Can one use pressure-treated lumber in metal plate connected truss construction? If so, are special plates or coatings required?

Question: 

I am trying to develop a guideline for my firefighters regarding initial fire attack in buildings with light-weight trusses. My concern is truss failure, especially when exposed to fire. Is there any information on failure time related to flame impingement? Any information about truss failure – especially in a fire condition would be helpful.

Question: 

What is the recommended standard spacing for open-web wood joists? I have seen them placed 24 in. O.C. Is this acceptable for a customer who will have an exercise room with 500 pounds of free weights? I understand there are problems with bouncy floors with 24 in. spacing. Is this true?

Question: 

We are concerned with SBCA’s BCSI-B1 Summary Sheet which under “Notes” makes a disclaimer. Our concern is if there would be an accident with our trusses and we point out that the bracing was not placed correctly according to SBCA documentation, which is sent with every job. If the accident goes to court, how will our attorney respond when the opposing attorney points out the disclaimer, which infers that the bracing we recommend must be flawed, otherwise it would not be disclaimed?

Question: 

I have a four-year-old house with glued open-web trusses. Both the truss manufacturer and the builder have admitted to me that the trusses were installed wrong. I have a problem with the suggested repair. I have hired a structural engineer and he suggested installing a 2x10 between each truss and removing the old truss. This would have to take place on both the first and second floors because all the trusses were installed wrong. The manufacturers want to install six strongbacks on each floor, hoping this will tighten them up.

Question: 

I have a 29 x 72 mobile office with a 2-foot deep wooden truss above the ceiling that a client is required to sprinkler. Is there any way to avoid sprinklering above the gypboard ceiling?