For decades, SBCA Jobsite Packages have helped component manufacturers (CMs) provide handling and installation guidance to their customers with every order. These pre-assembled packages of instruction documents, attached to truss deliveries in a zippered plastic bag, are now available in a digital format.

SBCA’s library of technical design and installation best practices has been expanded over the past year to help CMs navigate a wide array of code-related challenges in their markets.

Question: 

The Gypsum Association “Fire Resistance Design Manual” (GA-600-12) lists file RC2601 with two layers of 5/8 in. gypsum wallboard (GWB) on wood joists.

Question: 

I am a building inspector and have some questions regarding how to apply IBC 2012 2308.8.5 (IRC 2012 R802.8) (similar IBC 2015 2308.4.6 & IRC 2015 R802.8) to trusses, especially those with high heels:

Question: 

I have recently heard of a problem with fire-retardant-treated wood (FRTW) trusses that were manufactured and installed in 1965-1980. I was searching for more information, since my job involves the protection of property in our member school districts. I had heard that the trusses make of FRTW during that time period can or will become corrosive to the hardware and the trusses will fail.

Question: 

What are the requirements for installing valley sets over roof trusses? I am interested in nailing and support conditions. Some engineers ask for the bottom chord of the valley truss to be ripped to match the roof pitch of the underlying trusses. Is this necessary? How can I calculate values for uplift resistance for the building inspector?

Question: 

I was wondering if you have any information or anecdotes relating to the deflection performance of long span scissors trusses? We recently sold a job with 70 ft. long scissors trusses. The customer is in the process of installing the trusses and doesn't like the deflections he is seeing. To make matters worse, the scissors trusses are framing into a valley set (which we provided) that is erected on 35 ft. Howe trusses. The Howe trusses are exhibiting very little deflection. Any ideas?

Question: 

What are the requirements for installing “valley set” overlay roof trusses? I am interested in nailing and support conditions. Some engineers ask for the bottom chord of the valley truss to be ripped to match the roof pitch of the underlying trusses. Is this necessary?

Question: 

In a small scale multi-family residential project, I'd like to use a wood truss floor-ceiling assembly to achieve a one hour separation between units. I'd like to directly attach the drywall to the underside of the trusses & use the truss space for ducts & lighting (the floor above will be lightweight concrete on plywood sub-floor). UL assemblies do not seem to address the duct/light penetrations in such an assembly. Can I achieve a one-hour rating in such an assembly and how are penetrations addressed? Can the ducts in the truss space serve both units above and below?