Question: 

We are planning to add 1/2 in. cement board and 3/8 in. quarry tile to a kitchen floor. We need to know if the floor trusses will handle the additional weight. The floor trusses are 19.2 in. O.C. and the loading numbers are 40-10-0-5. What do these numbers mean?

Question: 

I am reviewing a truss package that includes multi-ply trusses. Where do I find the requirements for the attachment of the individual trusses to each other (nails and/or bolts)? Is this a requirement that the structural engineer of record needs to supply or is it the responsibility of the truss manufacturer to design?

Question: 

What are the requirements on the permanent bracing of bottom chords? Can gypsum board diaphragms be used?

Question: 

I need to know how to repair a hole that has been drilled through a truss. In installing the wiring we improperly put the wires through the truss and now need to know the proper way to repair it.

Question: 

How often are trusses repaired?

Question: 

Is it common practice for the supplier/distributor of a truss to provide a publication regarding temporary bracing with the delivery of the material?

Question: 

In a small scale multi-family residential project, I'd like to use a wood truss floor-ceiling assembly to achieve a one hour separation between units. I'd like to directly attach the drywall to the underside of the trusses & use the truss space for ducts & lighting (the floor above will be lightweight concrete on plywood sub-floor). UL assemblies do not seem to address the duct/light penetrations in such an assembly. Can I achieve a one-hour rating in such an assembly and how are penetrations addressed? Can the ducts in the truss space serve both units above and below?

Question: 

Does the NFPA sprinkler standard address sprinkler loading? If so, how and where do I buy it? What other information do you have on sprinkler loading? How do other truss companies price jobs for sprinkler loading the plans do not include a sprinkler layout or even say what size/type of sprinkler system will be used?

Question: 

Are there any published studies or guidelines on the fire rating of floor trusses built with 2x3 lumber?

Question: 

The industry suggests notching the gable end truss to support the overhang. Is this wise? What about a structural gable, or a gable designed with drag loads, or one with only partial bearing? How safe is it for a framer working with a truss that has the top chord cut repeatedly?