Question: 

We have a customer that bought trusses in June. The trusses were shipped [ and one month later are] being set. The chords have weathered and bowed. What is the industry standard for dealing with this problem? What is our liability in this situation? We were not aware of any delays on the customer’s part and shipped as requested. Note: These trusses are 62 ft. scissor trusses.

Question: 

We keep having problems with dry wall joints raising on the vaulted bottom chords in the track homes that we are building. The joints run from front to back of the house and the trusses bear on the side walls. The trusses are mostly 2-point bearing (a few in the front and back of the building are tri-bearing). The trusses span 40 ft. and have a 4/12 pitch with a tile roof. Is it common to have dry wall problems as the trusses deflect? How long should the roof be loaded before hanging sheetrock? Should the heel of the truss be allowed to slide out on the top plate?

Question: 

I am a building designer on a salt storage building project. I would like to use metal plate connected wood trusses in the design. What should I specify for the metal connector plates?

Question: 

My framers are always complaining that the “trusses are bad.” I am looking for tolerance information that not only addresses the allowable variance in length and height, but also allowable variation in the top chord with regard to straightness (i.e. how straight should a pull string line from the top and bottom of top chord be?). Also, if trusses are set on a perfectly level wall, what variation is allowed from truss to truss (i.e. if I put a 10 ft. straight edge perpendicular to the trusses, how much can they vary in height, not just at peak or bottom but all along the top chord)?

Question: 

Are there any schematics available on how to horizontally brace a 7/12 pitch roof?

Question: 

My company supplied roof trusses for a hotel project. The building inspector shut the project down because the trusses were not designed to account for additional snowdrift loading. The construction plans did not contain any snowdrift loading information. The architect is claiming it is our responsibility to determine drift loading, therefore we must fix the problem. Do you have any documentation to help us dispute the architect’s claim?

Question: 

We are concerned with SBCA’s BCSI-B1 Summary Sheet which under “Notes” makes a disclaimer. Our concern is if there would be an accident with our trusses and we point out that the bracing was not placed correctly according to SBCA documentation, which is sent with every job. If the accident goes to court, how will our attorney respond when the opposing attorney points out the disclaimer, which infers that the bracing we recommend must be flawed, otherwise it would not be disclaimed?

Question: 

I am currently putting together a set of truss specifications for a set of structural plans. I am interested to know of the most current publication that may specify industry standards in truss components (i.e. metal connector plates, wood quality and connection quality). Do you have any suggestions?

Question: 

Our home caught fire last month and burned partly through a tongue and groove ceiling to the trusses. Some are charred. Our contractor did a moisture meter test. An engineer for the insurance company said the trusses were only smoke damaged & the moisture meter test is invalid (it can be set to read anything). I found one article on charred trusses, but it’s pretty vague. We do not feel safe with the insurance engineer’s assessment because some of the trusses are obviously charred. We hired an engineer who agreed with us.

Question: 

We have been specifying laminated veneer lumber (LVL) beams for some time now. The plans usually state, “Beam to be engineered and supplied by truss manufacturer.” What kind of liability issues do I need to watch out for?